2024 NEW ASPHALT

2024 NEW ASPHALT ROADS


 

 

       ROAD NAME                            DISTANCE                 LOCATION                                                 ESTIMATED START/END DATE

JOHN CREECH RD                             1.62 MILES                   HWY U TO US 61                                                  LATE SUMMER/FALL 2024

CREECH RD                                          0.57 MILES                   JOHN CREECH RD TO THE BRIDGE            LATE SUMMER/FALL 2024

SADDLE RIDGE RD                            1.39 MILES                    HWY KK TO THE END                                       LATE SUMMER/FALL 2024

 

 

THE COMPLETION OF NEW ASPHALT ROAD PROJECTS DEPENDS ON SEVERAL FACTORS.  WEATHER, SCHEDULING, EQUIPMENT, LABOR, BUDGET, FEMA EVENTS, AND OTHER FACTORS CAN DELAY OR CANCEL PROJECTS.  THESE PROJECTS ARE ALSO DEPENDENT ON LANDOWNER COOPERATION IN SOME CASES, (COST SHARE ROADS).