ROADS WILL REMAIN OPEN TO TRAFFIC DURING CONSTRUCTION WITH SOME DELAYS POSSIBLE.
WORK WILL BE DONE PRIMARILY MONDAY THROUGH THURSDAYS, 6AM-4:30PM. SOME VARIATIONS TO DAYS OR TIMES MAY BE NECESSARY TO COMPLETE PROJECTS.
ROAD NAME DISTANCE START/COMPLETION DATE
- Thornhill Cemetery Rd (Hwy 47 to the bridge) 0.98 miles COMPLETED MAY 11TH
- Frenchman’s Bluff Rd 2.71 miles COMPLETED MAY 18TH
- Walker Rd 3.6 miles COMPLETED JUNE 8TH
- Jacks Rd (Hwy KK to Absolut Ln) 1 mile SUMMER/FALL
- Nineveh Rd 0.38 miles SUMMER/FALL
- Paulsmeyer Rd 0.68 miles SUMMER/FALL
- Adams Rd 0.52 miles SUMMER/FALL
- Colbert Ln 0.56 miles SUMMER/FALL
- Mashek Rd 0.2 miles SUMMER/FALL
- Taylor School Rd 0.6 miles SUMMER/FALL
- Gibison Rd 0.53 miles SUMMER/FALL
- Spielhagen Rd 1.89 miles SUMMER/FALL
- E. Cappel Rd 0.48 miles SUMMER/FALL
- Brandes Rd 1.03 miles SUMMER/FALL
- N. Cappel Rd 0.73 miles SUMMER/FALL