ROADS WILL REMAIN OPEN TO TRAFFIC DURING CONSTRUCTION WITH SOME DELAYS POSSIBLE.
WORK WILL BE DONE PRIMARILY MONDAY THROUGH THURSDAYS, 6AM-4:30PM. SOME VARIATIONS TO DAYS OR TIMES MAY BE NECESSARY TO COMPLETE PROJECTS.
THIS IS A PROJECTED LIST AND TIMETABLE, DUE TO SEVERAL FACTORS THIS LIST MAY BE CHANGED. THIS LIST WILL BE UPDATED PERIODICALLY.
ROAD NAME DISTANCE LOCATION START/COMPLETION DATE
- Adams Rd 0.53 miles COMPLETED
- Bell Rd 1 mile
- Bickel Hollow East 0.25 miles
- Bickel Hollow West 0.47 miles
- Burr Oak Rd 0.11 miles
- Creech School Rd 0.88 miles Gravens Rd to S. Ridge Rd
- County Farm Rd 2.59 miles
- Corso Rd 1.14 miles COMPLETED
- Hammett Rd 1.48 miles
- Harrell Rd 1.16 miles IN PROGRESS
- Highland Prairie Rd 0.71 miles MAY
- Hobart Rd 0.44 miles COMPLETED
- Keeteman Rd 0.74 miles EARLY MAY
- Mcintosh Hill Rd 2.34 miles APRIL 24TH START
- Myers Rd 3.18 miles
- N Lindsey Rd 1.86 miles LATE APRIL/EARLY MAY
- Point Rd 1.68 miles
- Rahmier Rd 1.03 miles MAY
- Ridge Rd 4.35 miles
- Scott Rd 1.56 miles
- Wilson Rd 0.59 miles COMPLETED
TOTAL 28.09 miles